Member Search

FIDIC (Red Book) – Pitfalls in Qatar for the Unwary

Published: Friday, July 10, 2015

Federation  International Des  Ingenieurs  –  Conseils  (“FIDIC”) (from  French,  the  International  Federation of  Consulting  Engineers) in  1999  published The  Red  Book:  Conditions  of  Contract  for  Construction  for  Building  and  Engineering  Works  Designed  by  the  Employer (“Red  Book”).  In  Qatar,  FIDIC  Red  Book  is  the  most  commonly used  standard  form  contract  for  construction  and  engineering  works  where  most  or  all  works  are  designed  by,  or  on  behalf  of,  the  employer. 

FIDIC  forms  are  largely based  on  English common  law  principles, however  these  common law  roots  do  create  certain paradoxes  when  the  contract  are  used  in  civil  law  jurisdictions  like  most  of  the  Gulf  States.  This  problem  is  further  complicated when  the  contractors and  employers,  in  a  Qatari legal  environment,  follow a  general  practise of  agreeing  to  a  standard FIDIC  form  as  opposed  to  a  bespoke contract  in  the  interest  of  saving  time.  However,  it  has  been  proved  time  and  again  that  such  a  practise may  not  only  prove  detrimental to  the  parties but  may  also  adversely  impact the  time  and  cost  thereby jeopardising  the  successful completion  of  the  entire  project. 

In  the  subsequent  sections, we  analyse  some  of  the  pitfalls  in  detail  and  also  indicate precautionary  measures  which  may  be  taken  to  avoid  such  traps.

(a)  Provision  of  indemnity

Generally,  indemnity provisions  are  among  the  most  vigorously  debated clauses  during  contract negotiations  in  construction contracts  in  the  Middle  East.  An  indemnity obligation  is  meant  to  compensate the  affected  party  to  a  contract  from  losses  arising from  death,  personal injury  and  property damage  caused  by  the  counterparty.

In  common Law,  an  indemnity may  also  allow  a  claimant to  frame  its  claim  in  debt  as  opposed  to  breach  of  contract,  however, in  civil  law  indemnity  is  a  provision of  the  contract and  subversion  of  the  same  would  be  breach  of  contract  resulting in  termination  and  would  not  be  treated as  a  debt.

The  Qatari Courts  consider  a  claim  under  the  indemnity in  the  same  manner  as  a  breach of  any  other  term  of  the  contract. Clause  17.1  of  the  FIDIC  Red  Book,  which  seems  to  be  worded  to  operate  in  a  common law  environment,  must  be  amended to  commensurate  with  the  requirements of  the  Qatari law.  One  of  the  advantages of  having  an  indemnity  provision in  a  contract is  that  the  parties  become aware  of  the  probable  breaches which  may  result in  a  dispute in  advance  and  have  the  opportunity  to  take  measures to  avoid  the  same  from  the  commencement date  of  the  contract. 

(b)  Decennial  Liability 

The thriving  construction  industry in  the  middle-east attracted  various  internationally  renowned big  players  from  diverse  legal  jurisdictions.  Engineers and  construction  companies coming  from  both  common  law  and  civil  law  jurisdictions are  used  to  negotiating  and  limiting  their  exposure  in  the  defects liability  period.  The  requirements  and  duration  of  the  defects liability  period  have  a  direct impact  on  the  prices  quoted to  the  employer for  any  construction project.  However,  the  defect  liability period  is  treated quite  differently  in  Qatar.

The defect  liability  period, known  as  the  decennial  liability in  Qatar,  is  one  of  the  typical concepts  of  the  Qatari  jurisdiction and  may  prove  to  be  an  unpleasant surprise  for  any  new  comer. Decennial  liability  is  a  strict liability.  The  Qatari law  provides  that  the  contractor and  designer  of  the  works  would  remain jointly  liable  for  a  period of  ten  years  from  the  completion  of  the  works. The  decennial  liability covers  total  or  partial  collapse or  fault  in  the  buildings even  if  the  collapse  or  fault  has  resulted  from  a  defect in  the  land  itself  provided that  the  defect threatens  “sturdiness  or  safety”.  Decennial liability  may  not  be  contractually limited  or  excluded.

(c)  Limitation  of  Liability

Under  the  Qatari  laws,  parties  generally have  a  fair  amount  of  freedom  to  agree  caps  on  their  eventual  liability (subject  to  various provisions  in  the  applicable  civil  code).  Generally, during  contract  negotiation, clause  17.6  of  the  FIDIC  Red  Book  (Limitation  of  Liability)  is  typically  amended to  insert  additional “carve  outs”  or  exceptions  to  put  a  cap  on  the  eventual liability  of  the  parties.  Most  of  the  contractors  operating in  the  Qatari legal  environment  do  not  realise that  even  after  inserting  a  caveat  in  clause  17.6,  there  still  remain  some  clauses  which  pierce  through the  limitation  of  liability.  Clauses worth  mentioning  here  are  clause 18  (Insurance)  and  clause  17.1  (Indemnities)  which  need  special attention  to  ensure the  liability  of  the  parties is  limited  to  the  value  of  the  contract.  Additionally, instances  like  fraud  or  negligence may  be  treated in  a  manner under  the  Qatari laws  which  may  pierce  through the  limitation  cap  prescribed  under  the  contract. However,  it  is  not  possible to  contractually  limit, for  example  by  way  of  a  cap  on  liability, the  statutory  decennial liability  relating  to  total  or  partial  collapse of  or  fault  in  in  civil  structures. 

(d)  Commencement  Date

A  feature of  the  FIDIC  Red  Book  1999  edition is  the  reorganisation  of  various  contractual terms,  now  following a  more  logical format.  Accordingly,  clause 8  now  deals  with  all  topics  related to  commencement  of  work,  programming, delays  and  suspension during  the  course of  the  works. 

Clause  8.1  of  FIDIC  Red  Book  asserts  a  commencement  date  of  42  days  after  the  contractor receives  the  letter of  acceptance,  unless particular  conditions  of  the  contract provide  otherwise.  The  engineer  gives  the  contractor at  least  seven  days’  notice of  the  commencement date.  The  contractor commences  the  design and  execution  of  the  work  “as  soon  as  reasonably practicable”  after  the  commencement  date,  proceeding  with  works  “with  due  expedition and  without  delay”. 

In  practice, as  described  above, many  construction  contracts in  Qatar  are  negotiated  with  no  tendering/bidding  whatsoever, or  with  significant post  tendering  or  bidding  negotiations. FIDIC  has  introduced the  requirement  to  reach  agreement and  then  create a  letter  of  tender  and  letter  of  acceptance  prior  to  signing the  contract,  which  is  somewhat naïve  and  it  would  be  preferable  to  include  these  as  agreed terms  in  the  contract.  Even  if  the  particular  conditions of  the  contract can  easily  be  amended  but  it  is  suggested  it  would  be  far  simpler if  FIDIC  followed the  model  of  other  standard forms  of  contracts, introducing  the  commencement date  as  agreed and  therefore  inserted into  the  contract particulars. 

However,  care  must  be  taken  while  drafting  the  letter  of  intent.  It  is  common for  this  letter to  mark  the  commencement  of  onsite  works, though  negotiations  of  minor  issues have  yet  to  be  finalised. Therefore,  it  is  critical  this  letter  not  be  interpreted as  the  letter of  acceptance,  so  drafting  must  be  meticulous.

The  Harmonised Multilateral  Development  Bank  (MBD)  Pink  Book  rewrites clause  8.1  to  require  for  the  following conditions  precedent  to  be  fulfilled by  the  parties before  the  commencement of  works: 

i.  contract signed  by  both  parties;

ii.  receipt by  the  contractor of  “reasonable  evidence of  the  employer’s financial arrangements”;

iii.  site  possession  given  to  the  contractor;

iv.  provision of  any  advance payment  and  corresponding guarantee/bond. 

The  amended contract  asserts  the  contractor’s  option to  terminate  if  the  conditions precedents  are  not  fulfilled  within 180  days  of  the  letter of  acceptance,  introducing additional  complexity  to  commencement  of  work  and  ignoring  the  possibility  that  site  possession is  not  always necessary  –  or  in  fact  advisable  –  at  the  outset  of  contractor  works. 

(d)  Conditions  Precedent 

The  most  contentious  provision of  the  FIDIC  1999  Red  Book  is  the  requirement under  its  clause 20.1,  which  is  a  condition precedent  to  any  claim  for  extension  of  time  or  cost. 

Reference  to  clause  20.1  elsewhere  in  the  contract demonstrates  that  if  the  contractor is  not  compliant if  he  forfeits any  entitlement  to  an  extension of  time  or  cost  irrespective of  relevant  circumstances. 

Clause  20.1  states  that  a  contractor ‘shall  give  notice to  the  Engineer, describing  the  event  or  circumstances giving  rise  to  the  claim. The  notice  shall  be  given  as  soon  as  practicable, and  not  later  than  28  days  after  the  Contractor became  aware,  or  should  have  become  aware, of  the  event  or  circumstance’  .

Therefore,  a  prudent  contractor should  never  assume that  conflicts  can  be  resolved informally,  and  instead always  take  care  to  comply with  the  timescales set  out  in  sub-clause  20.1  and  submit the  required  notice within  the  prescribed period  of  28  days.  The  only  area  in  which  the  contractor is  given  any  leeway  is  where  it  was  reasonable to  conclude  he  could  not  have  been  aware  of  the  event  or  circumstance giving  rise  to  the  entitlement to  extra  time  and/or  cost.  It  is  suggested  that  a  prudent contractor  should  adopt  the  practice of  having  at  least  one  review  in  every  28  day  period to  assess  whether any  notice  ought  to  be  given  under  contract.

Although  not  a  condition precedent  of  the  entitlement  to  make  a  claim,  clause 20.1  requires  the  contractor  to  keep  records, making  those  records available  to  the  engineer.

Within  42  days  of  the  contractor becoming  aware  (or  should  have  become  aware) of  the  claim, or  over  a  longer  period if  the  engineer agrees,  the  contractor must  send  a  fully  detailed claim  with  supporting particulars.  This  claim  will  be  treated  as  interim  but  it  must  be  updated at  monthly  intervals. The  final  claim  must  be  sent  within 28  days  after  the  end  of  the  effects  resulting from  the  event  or  circumstance that  gave  rise  to  the  claim. 

The  requirements to  submit  this  claim  within 42  days  and  to  update the  claim  are  not  conditions precedent  in  the  same  way  as  the  initial  notice, though  it  is  clear  failure to  comply  with  this  requirement will  prejudice  the  contractor’s  position. 

The  engineer has  42  days  after  receiving the  claim  to  respond  with  approval  or  disapproval  and  detailed  comments. Monthly  payment  certificates will  include  the  amounts  the  Engineer  approves within  the  Contractor’s claim. 

(e)  Application  of  Laws 

When  using  a  FIDIC  Reb  Book,  parties  must  consider  the  interplay  of  the  applicable laws  of  the  contract  with  the  Qatari laws  (place  where  the  works  under  the  contract  would  be  performed) specifically  in  respect of  the  interpretation  of  the  terms  of  the  contract.  Conflicts between  the  contractual terms  and  the  applicable  law  of  the  contract  may  be  avoided by  making  necessary, amendments  and  carve-outs to  the  FIDIC  Red  Book.  Some  of  such  instances which  may  prove  detrimental  to  both  the  employer  and  the  contractor and  must  be  addressed  during contract  negotiation  stage  are  discussed below. 

i.  Liquidated  Damages

Whilst using  the  FIDIC  Red  Book  in  Qatar, it  must  be  remembered  that  the  Qatari laws  under  Law  No  (22)  of  2004  (“Civil  Code”) permits  the  parties, to  agree  to  a  level  of  liquidated damages.  There  is,  however,  no  distinction  in  Civil  Code  between  penalties and  liquidated  damages, so  parties  are  able  to  agree  that  penalties  will  be  levied as  damages  for  delay  to  completion.  There  are,  however, certain  provisions  of  Qatari  law  that  may  assist  an  employer,  whose  sole  remedy is  liquidated  damages, and  the  actual losses  incurred  to  him  may  not  be  reflected  fully  in  the  agreed  cap  to  the  eventual  liability. 

In such  instances,  Article 266  of  the  Civil  Code  permits  the  court  to  intervene,  despite what  is  agreed, to  adjust  the  level  of  liquidated  damages to  reflect  a  party’s  actual loss.  Article  266  of  the  Civil  Code  provides  that:  “The  compensation agreed  upon  will  not  be  payable  if  the  debtor proves  that  the  creditor  has  not  sustained any  detriment,  and  the  court  may  reduce the  compensation  below  what  was  agreed  upon  if  the  debtor  proves that  the  assessment was  exaggerated  to  a  considerable degree,  or  that  an  obligation has  been  obligation in  part.  Any  Agreement  that  rules  otherwise is  null  and  void.”

ii.  Dispute  Resolution

The  influx of  contractors  based  in  the  United  Kingdom and  the  United States  in  the  Qatari  construction market  meant  that  there  was  an  automatic preference  by  the  contractors  to  resolve  any  dispute  through arbitral  proceedings,  based  and  governed under  the  laws  of  their  home  countries. The  Qatari  law  allows  the  parties  to  agree  to  such  an  arrangement  and  it  also  ensures  comfort of  the  parties who  end  up  agreeing  to  a  jurisdiction of  their  own  choice  for  the  resolution of  the  disputes.

However,  in  majority  of  cases,  arbitral awards  consequent  to  such  arbitration proceedings  are  unlikely to  be  ratified/enforced  within the  Qatari  jurisdiction. This  is  simply because  of  various requirements  of  form  and  procedure that  have  to  be  fulfilled during  the  arbitration proceedings  in  order  for  the  arbitral  award  to  be  enforceable  in  Qatar. 

Therefore,  the  parties  to  the  contract must  ensure  that  the  applicable laws  and  rules  of  arbitration must  not  be  in  conflict with  the  Qatari law  to  ensure prompt  and  efficient ratification  of  arbitral awards.

iii.  Consequential  Losses 

The  Qatari laws  allow  the  parties  to  agree  to  any  term  in  a  contract.  Clause 17.6  of  the  FIDIC  Red  Book  attempts to  exclude  the  consequential  losses and  limit  the  liability  of  the  parties. However,  in  various instances  (like  fraud, negligence  and  pollution)  the  provisions  of  the  Qatari law  may  override the  terms  of  the  contract to  determine  the  extent  of  liabilities  on  the  parties to  the  contract.

Foreign  contractors, specifically  the  ones  based  in  a  common law  jurisdiction  and  have  established a  branch  or  an  entity in  Qatar  to  participate  in  the  construction and  engineering  works  where  the  state  is  the  ultimate employer,  must  be  wary  of  the  aforementioned  risks.

Qatar  has  moved  steadily in  recent  times  to  become the  hub  of  international  sporting events  in  the  Middle  East  region.  The  2022  FIFA  World  Cup  is  scheduled to  take  place  in  Qatar  in  2022.  Qatar  would  be  the  first  Arab  country  to  host  the  World  Cup  and  this  would  be  the  first  time  the  World  Cup  would  be  held  in  the  Middle East  region.  Also,  the  15th  Asian  Games, officially  known  as  the  XV  Asiad,  Asia's Olympic-style  sporting  event, were  held  in  Qatar  in  2006.

Hosting  of  international  sporting events  of  such  demeanour,  prestige and  recognition  around the  globe  ensured that  Qatar  and  its  codified laws  remain  in  constant  limelight on  the  international stage.    Qatar  has  risen  to  the  occasion and  has  deployed a  constant  effort at  all  levels to  develop  its  laws  so  that  the  country  is  able  to  more  capably meet  the  enormous challenges  that  lay  ahead.

Laws  pertaining to  construction  and  engineering  are  no  exceptions to  this  on-going ‘change’  phenomenon  in  Qatar.  With  a  plethora of  international  firms  and  contractors coming  to  Qatar  to  play  their  part  in  meeting the  ever  increasing demands  of  the  construction  and  engineering  industry, we  expect  that  the  local  laws  would  continue  to  evolve,  change and  refine  towards betterment.

Sultan M. Al-Abdulla
Sultan Al-Abdulla & Partners
Country:
Qatar
Practice Area:
Full Service
Website:
Phone Number:
+974 44 42 0660
Fax:
+974 44 42 0663
Mr. Sultan Al-Abdulla is the founder of Sultan Al Abdulla & Partners (SAP). As part of his practice, he provides legal services to a wide range of corporate and institutional clients. Prior to establishing his practice in 1999, Mr. Al-Abdulla worked for Qatar Petroleum (QP) for 22 years. During the last three years of his career with QP, he served as Managing Counsel and in this capacity represented the government of the State of Qatar and QP and its subsidiaries in major transactions as lead negotiator. Mr. Al Abdulla in his private practice, has counseled, and negotiated on behalf of, local and multinational clients, major business transactions and projects. As a litigator, he represents clients before all tiers of courts in Qatar up to the Court of Cassation. He is a member of the International Bar Association and the Association of International Petroleum Negotiators and Inter Pacific Bar Association

Member Introduction

The Lawyer Network in numbers

0+

Members Firms

0+

Countries

0+

Practice Areas

0+

Member Firms
Total Staff